The Realistic Range

Most garage conversions in Florida run 8-14 weeks total, split roughly between permit review and actual construction. Projects requiring HVHZ structural engineering (Miami-Dade, Broward) or flood zone documentation tend to land on the longer end of that range.

Week-by-Week Breakdown

PhaseTypical Duration
Design & permit package prep1–2 weeks
Permit review & approval2–4 weeks (longer in HVHZ counties)
Framing, electrical, HVAC rough-in2–3 weeks
Insulation, drywall, finishes3–4 weeks
Final inspections & close-out1–2 weeks

What Extends the Timeline

The two biggest timeline risks are an incomplete permit submission (see our Permit Requirements guide) and discovering a flood zone or structural issue mid-project that wasn't caught during design (see our Flood Zone guide). Both are avoidable with the right upfront review.

"The projects that run long almost always had a permit or flood zone surprise mid-build. The ones that stay on schedule had all of that checked before we ever picked up a hammer."

Get a Straight Answer

Tell us what's going on — we'll give you honest guidance on cost and what's realistic. No obligation.

Please enter your first name.
Please enter your last name.
Please enter a phone number.
Please enter a valid email.
Please select one.
Please select one.

Free · No obligation · We respond within 24 hours

Got it — thank you!

A D&Co Homes Project Manager will reach out to you shortly with next steps for your property.